JAPAN GAS CORPORATION (JGC) Part 1

Written by 
Rate this item
(0 votes)

JAPAN GAS CORPORATION (JGC)

Part 1- Project

Logistics and Project Management date: 2003

Featuring

3 Units Reactors
1 unit Reactor, L – 14.230 x W – 5.930 x H – 6.330 meters, 37.5 MT
1 unit Reactor, L – 14.230 x W – 6.007 x H – 6.330 meters, 37.6 MT
1 unit Reactor, L – 14.230 x W – 6.050 x H – 6.330 meters, 37.5 MT
From South Harbor, Port of Manila to JGC Job Site at Rio Tuba Nickel Mining Corporation, Rio Tuba, Palawan

Pier side receiving at South Harbor, Port of Manila

Transport to Port Storage Area

Mounting on Beams and Stools at Port Storage Area

3 Reactors mounted on Beams and Stools at Port Storage Area

Roll-On LCT Barge at Port of Manila, Lashing / Securing, Steaming to Rio Tuba Jetty, Transport and delivery to jobsite